Sorting by date in Project 2013 RRS feed

  • Question

  • I've sorted my tasks by start date but they are still displaying out of order. See below. How do I fix this?


    1.3.1.1.6    A         Mon 12/4/17 Fri 4/6/18
    1.3.1.1.6.1 A1 Mon 12/4/17 Fri 3/23/18
    1.3.1.1.6.2 A2 Mon 12/11/17 Fri 4/6/18
    1.3.1.1.4    B         Mon 12/11/17 Fri 2/9/18
    1.3.1.3 C         Wed 11/22/17 Fri 6/15/18
    1.3.1.3.1     C1 Wed 11/22/17 Fri 1/5/18
    1.3.1.3.1.1 C1a Wed 11/22/17 Wed 12/6/17
    1.3.1.3.1.2 C1b Wed 12/6/17 Wed 12/20/17
    1.3.1.3.1.3 C1c Wed 12/20/17 Fri 12/29/17



    Friday, January 5, 2018 10:16 PM

All replies

  • LinV160 --

    From your description, it appears that your project contains summary tasks.  If this is true, then the sorting will only apply to the subtasks in each summary section.  Does that explain what you are seeing?  Let us know and we will try to help you.


    Dale A. Howard [MVP]

    Friday, January 5, 2018 10:22 PM
    Moderator