Deliverables are not migrated to Project Server 2010 RRS feed

  • Question

  • Hi

    After a full database attach migration from Project Server 2007 to Project Server 2010, deliverables are not migrated to the 2010 environment. Everything else has been migrated correctly - risks, issues and documents. Has anyone heard of this before and know what the reason might be?

    JR

     

    Wednesday, November 16, 2011 8:51 AM

All replies

  • Hi .JR.

    a question about this issue: after the full database attach, have you update using "Bulk update Project Sites" tool under server setting?

    Have you any error in ULS log when you try to acces to deliverables?

    Best Regards,

    Paolo O.