AssignmentActualWork > ActualWorkBillable RRS feed

  • Question

  • Hello;
    We are working on Project Server 2010 with August 2017 CU. On one task there is mismatch between assignement and timesheet. In MSProject (winproj) on this task for two resources (one is generic, other is work resource) I see actual work that is equal planned work. In timesheet this work type resource has reported totaly different values. Cheeking [MSP_EpmAssignmentByDay_UserView] on that task nad resource i got over 1400h (AssignmentActualWork)  in [MSP_TimesheetLine_UserView] only 90h (ActualWorkBillable). We use single entry mode, nad allow actual only from timesheets.

    Task is accepted, published.

    Is it possible to update assignments on this task so it would corresopnd with reported actual work billable?

    Wednesday, December 6, 2017 11:00 AM