Duration days wrong RRS feed

  • Question

  • First time using project. I put in the first task with start date as March 8th,2010 and duration days but it's showing finish date as 17th instead of the 15th. why?
    Thursday, February 7, 2019 10:14 AM

All replies

  • Hi Kudi2,

    How many days did you mention for the Duration? 

    If you give the duration as 8 days then the finish date would be 17th as 13 & 14 th are weekends. So project will by default ignore the weekends. If you want to include the weekends you need to customize the calendar.

    Hope, have answered your query.