Creating Custom Alerts at a Task Level in Project Online RRS feed

  • Question

  • Hi, I would like to configure Custom Alerts in Project Online. 

    That is, I will create 3 Custom Attributes called L1, L2 and L3 for Tasks.

    When I create a new task, I will specify values as below:

    L1 will have a value -5

    L2 will have a value -3

    L3 will have a value -1

    These values will be matched against the Tasks' due date and e-mail will be sent out to the Task Owner copying Manager whenever these dates are met. For instance, if the Due Date is 20th Dec 2016, on 15th (which is -5), an alert will go, then on 17th and then on 19th. 

    Is this possible to be achieved?


    Karthick S

    Thursday, December 22, 2016 2:12 AM

All replies

  • Hi,

    I think this feature is not available in Project Online.

    You may try to pull the assignments related data from Project Online to a SQL Server and build your notification system for custom alerts on top that.


    Regards,

    Atul Lal


    Please don't forget to mark it as answered, if your problem resolved or helpful.


    • Edited by Atul Lal Thursday, December 22, 2016 6:35 AM
    • Proposed as answer by Atul Lal Thursday, July 6, 2017 1:01 PM