Not able to deactivate a task in 2010 RRS feed

  • Question

  • I’m able to deactivate most of my task except for 1, even though the % complete is 0 on that yet I m not able to deactivate it. Please suggest.
    Thursday, April 3, 2014 7:18 AM

Answers

  • Please check if Actual start date has been added for the task, because the project ensure that any actuals added against a task no matter even if its 0% should not be deactivated.

    Sapna Shukla

    Thursday, April 3, 2014 7:27 AM
    Moderator

All replies

  • Please check if Actual start date has been added for the task, because the project ensure that any actuals added against a task no matter even if its 0% should not be deactivated.

    Sapna Shukla

    Thursday, April 3, 2014 7:27 AM
    Moderator
  • Thanks !