Resource Availability view from "Working/Unpublished Version" of schedules RRS feed

  • Question

  • Hi team,

    need help in having a view where we can see the availability of resources.

    for published version of data , I use resource center in pwa to get this info.

    any idea if we can configure pwa to pull the data from" unpublished/working" version of projects". 

    If the above isn't possible, any reliable way other than creating a master project which includes all su projects and use resource usage view?

    Some one suggested using " load summary assignments" when opening gone file, however it's not reliable....

    regards,

    lakshmi 

    Sunday, June 22, 2014 7:25 AM

All replies

  • Lakshmi

    Only published data informs availability or demand for resource.

    Have you considered using the "Proposed" booking type - this can be set for Resources on a Project in the Build Team from Enterprise Dialog Box (CTRL+T) in a project.

    Publishing the project does not generate assignments for resources but if you view Resource Availability Graphs from the Resource Centre in PWA you can elect to "include proposed bookings".


    Dominic Moss | MAPM Microsoft Certified Technology Specialist | Our Newsletter: PM News Project Server Specialists Project Server PRIME | Twitter: @Twitter | Facebook: @Facebook | Linkedin: Wellingtone

    Tuesday, June 24, 2014 3:44 PM