Update Project RRS feed

  • Question

  • Project - Status - Update Project

    What's the use of "Update work as complete through"?

    Saturday, April 18, 2015 12:42 PM

All replies

  • jack19855,

    It is simply a quick way to update progress for a whole project or just selected tasks, normally to the status date. My personal feeling is that it is of limited usefulness since progress is unique for each and every task and a blanket update may not give a true representation.

    You might find this similar thread also helpful: https://social.technet.microsoft.com/Forums/en-US/01d57ca7-18ea-4bd5-a905-bc755aff982e/update-project-options-for-update-work-as-complete-through?forum=projectserver2010general

    Hope this helps.

    John

    Saturday, April 18, 2015 3:05 PM