timesheet concept RRS feed

  • Question

  • I have questions about Timesheet's Project Server concept.

    These are sequence which I try to understand about Timesheet

    1) user add hr. in Timesheet table ,save and send to approve

    2) Project Manager want to  Publish Plan which are edited at their home so they open plan in client and then save them to existing project for update the latest plan.

    3) Task in Timesheet for User in 1) are duplicate

    The result is normal according to concept's Project Server,Isn't it?

    Does anyone confirm this?  Thank You :)


    • Edited by sasimasTHA Monday, November 11, 2013 4:38 AM
    Monday, November 11, 2013 4:21 AM

All replies

  • After I find the article about working offline. I think I get something wrong. 

    If I want to work offline, I have to select work offline menu in Manage Account and choose work offline in log in page.

    I shouldn't save as the same name to server because that make a duplicate task in Timesheet.


    • Edited by sasimasTHA Monday, November 11, 2013 11:34 AM
    Monday, November 11, 2013 11:33 AM
  • Hi SasimasTHA,

    I definitely confirm that you should use the "work offline" feature. This will allow you checking-out your project plan in your local cache and work offline. When back to the office, you simply have to connect again to Project Server, to publish then check-in your project.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS