locked
Project Server 2007 moving dates when using build team from enterprise. RRS feed

  • General discussion

  • I have a PM with a plan, doing some odd stuff. He has an existing plan, with multiple resources assigned. He adds a member to the team, from build team from enteprise. Without assigning that resources any tasks, the plan changes task end dates. Remove that resource from the team, and dates revert back. Never seen this one before. Any ideas?    
    • Changed type Nicholas Li Tuesday, February 1, 2011 2:03 AM
    Monday, January 31, 2011 2:37 PM

All replies

  • I would suggest posting this in the project server forums.  This forum is for System Center Essentials.  Project Server forums can be found here.  http://social.technet.microsoft.com/Forums/en-US/category/projectserver2010
    Ok, so I changed my name...you can still call me Tom if you like. It's a...jump...to conclusions...mat.
    My Blog Site: http://tmagnuson.wordpress.com
    Monday, January 31, 2011 2:45 PM