Set Calendar Project Online RRS feed

  • Question

  • I have 2 calendars and one to be as "Cheked-out". I had a problem and needed restart my Project Online and after that, never more I got edit or delete this calendar. How can I to edit this calendar and put it in a status thar dont will be "check-out"?
    Thursday, December 1, 2016 6:04 PM

All replies

  • Hi,

    If the calendar is checked out, you have to go to the PWA Server Settings, "Force check-in enterprise objects", then select "enterprise calendars" in the list. You should see your calendar, select it then click on "check-in".


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Friday, December 2, 2016 8:06 AM