none
Permissions needed for creating an OData report? RRS feed

  • Question

  • Hi,

    What are the users who have the necessary access rights to create a report OData in Excel (Project Online)

    Thanks

    Tuesday, September 6, 2016 2:26 PM

Answers

  • Hello,

    It depends what permission mode your PWA site is using:

    • Project Permisssion mode: the users need to be in a security group that allows "Access Project Server Reporting Service"
    • SharePoint Permission mode: the users need to be in one of the following groups: Administrators, Portfolio Managers, Portfolio Viewers

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS | MVP | Downloads

    • Marked as answer by Robert6156 Friday, September 9, 2016 8:10 AM
    Tuesday, September 6, 2016 7:07 PM
    Moderator