Resource time phased data in project server 2013/project 2013 RRS feed

  • Question

  • Hi all,

    I am using project server 2013 .

    one resource availability percentage is set as 80% ie 6.4 hrs per day. But when we are doin task assignment, only 5.6 is taken for a day and rest is pushed to next day ( i have noticed this in the timephased data in the task usage screen).
    for eg. if 6.4 work is assigned to the resources for a task with start date 1/1/2014 and end date 1/1/2014.  5.6hrs is taken for first day and 0.8 hr is moved to next day. Also the duration still shows as 1 eventhough task finish date is changed to 1/2/2014.

    Please help to understand is there any settings where 5.6 is taken for a day though the resource capacity is set as 80% ie, 6.4hrs.


    Thanks, Rose

    Wednesday, January 29, 2014 4:49 PM

All replies

  • Hi Rose,

    is there any chance you have auto leveling turned on?  Menu Resource > Leveling Options > Automatic.

    Wednesday, January 29, 2014 5:46 PM