    i am using sharepoint 2013 as a project manager , and i have this question:

    for the "Team leaders" permissions in the schedual , how can i manage their permissions, which means i want to give them full control but without giving them the ability to edit other team leaders tasks

    Sunday, November 16, 2014 8:29 AM

Answers

  • It would be to set unique permission for single tasks, that when a task is created, check the Team Leaders of this task, then grant full control permissions for the team leader to this task.

    this can be done through workflow or event receivers.