Backwards planing RRS feed

  • Question

  • I have on row 9 my final finish date and want now that he take on Row 8 the start date of row 9 and plan the day back which is in the duration, how can I do this.


    • Edited by Trycos Thursday, April 19, 2018 10:04 AM
    Thursday, April 19, 2018 10:04 AM

All replies

  • Hello,

    If your planning is set to schedule from finish date (Project > Project information > Schedule from: ), then if you link your 2 tasks as Task 8 being predecessor (finish to start) of Task 9, then it makes the job

    Tell me if this helps you

    Jeremy