MS Project Server 2007 - Task Updates Empty But PWA Dashboard Shows Approvals Waiting RRS feed

  • Question

  •  MS Project Server 2007 - Task Updates Empty But PWA Dashboard Shows Approvals Waiting. 

    There are project managers experiencing a strange issue.  On the PWA dashboard it shows that they have some number of Task Updates waiting for approval.  When they go to the approvals page there are none available for approval.

    What could be causing this and how do we get rid of it?

    Monday, December 10, 2012 8:27 PM

Answers

  • Sounds like similar to below thread & there is a workaround:
    http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/87bb427d-81bc-4cfb-a321-07d09e1a0050/

    HTH,


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    Thursday, December 13, 2012 12:20 PM

All replies

  • HI Michael,

    Please first check that if some filters are not in place in Approvals page pr any thing like that.  based on your feedback, it will pursued accordingly.

    Regards


    R A A

    Tuesday, December 11, 2012 9:35 AM
  • I confirmed that there are no filters in place.  The issue still exists.
    Tuesday, December 11, 2012 4:42 PM
  • Hi Michael,

     

    It will be beneficial if you can share some screen shots of both Dashboard page and Approvals page.


    R A A

    Thursday, December 13, 2012 11:52 AM
  • Sounds like similar to below thread & there is a workaround:
    http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/87bb427d-81bc-4cfb-a321-07d09e1a0050/

    HTH,


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    Thursday, December 13, 2012 12:20 PM