Substitue text in Start End Date Field RRS feed

  • Question

  • I am using Project 2010. I have multiple projects in one master plan. Is there a way to substitute 'TBD' in the Start End Date field?
    Monday, October 17, 2011 11:59 PM

Answers

  • Are your tasks manually scheduled?  If the tasks are manually scheduled you can type anything in the Start, Finish or Duration field that you wish.  If the tasks are automatically scheduled they have to show a date.

    However, you could remove the Start and Finish fields from the view and add text fields -- title them start and finish and enter whatever you'd like.

     

    I hope this helps.

     

    Julie

    Tuesday, October 18, 2011 12:40 AM