DPM 2010 - Tape Library Issue - Second Tape spans to 3 tapes. RRS feed

  • Question

  • The scenario is this,

    Protection Group : protect the Exchange 2010 servers.

    Tape Library : 2 drives.

    The daily backup will be D2D & D2T .  The D2T for daily is 2 tapes (one for local site & another is for Off-site)

     

    The retention period has the following :

    D2D : 2 days

    D2T 5 weeks (long term)

    D2T (mth) : 120 months (long term)

     

    Now, if  I were to take off the 120 months , will it resolve the issue ?

    2nd question, how can I do another protection group on the same Protected group but retention is 120 months ?

     

    TQ & kindly advice,

     

    Regards,

    Bernard Khoo 

    Tuesday, August 9, 2011 7:23 AM

Answers