The tasks are not appearing in MPP (but appears once we select show all subtasks) RRS feed

  • Question

  • Hi,

    when i open a MPP, none of the tasks are appearing in the task tab, but when i select view--> outline-->show all subtasks, it appears.

    Please let me know what is the option to hide all tasks when the user opens a mpp.

    Thanks!
    Shamsuddeen

    Friday, December 13, 2013 12:47 PM

All replies

  • Hi Shamsudeen,

    As far as I know, there is not such an option.

    The project plan will be displayed as it was saved at the last opening. Meaning if the project manager reduce all tasks then save and close, the plan will be as is for the next opening.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    Friday, December 13, 2013 1:21 PM
    Moderator
  • To automate record a macro of you hiding all subtasks then call that macro from the BeforeClose event

    Rod Gill

    The one and only Project VBA Book

    Rod Gill Project Management

    Saturday, December 14, 2013 7:49 AM