Timesheet times and Actual work issue RRS feed

  • Question

  • Hi all,

    We have Project Server 2010 +SP1 + June CU + October CU, with the databases imported from Project Server 2007. We have also Project Professional 2007.

    At Server Settings, in Time and Task Managment, Task Settings and Display is checked the option "Only allow task updates via Tasks and Timesheets", to don´t allow to modify the Actual Work from Project Professional.

    Ok. The issue is all ok, but when I´m going to check in Project Professional the Actual Work in a Task, we don´t know why, but it´s added a bit of time to each period of time. Example:

    In a Timesheet of a Task we entered for a week: 2h, 2h, 2h, 2h, 2h.

    After in Profect Professional see the Actual Work: 2.1h, 2.1h, 2.1h,2.1h,2.1h

     

    Did Anyone experience a similar issue??

     

    Thanks in advance!


    Miguel Soler
    Wednesday, November 30, 2011 6:45 PM

All replies

  • Make sure that your project schedule calendar hours per day matches your hours per day in the options.

    Cheers!


    Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA
    www.WhartonComputer.com
    Wednesday, November 30, 2011 10:23 PM
    Moderator
  • Hi Michael,

     

    Yes, it is the same calendar, Standard and 40 hours per week.

     

    Any more ideas??

     

    Thanks!


    Miguel Soler
    Thursday, December 1, 2011 9:38 AM