Inconsistency of baselinedate between project pro and OData RRS feed

  • Question

  • Hello,

    For many projects in our Project Server, when connecting to the Project Server OData api (with Power BI) and looking on the Projet Baslines table, on the ProjectBaselineModifiedDate field, we get a date much later then the date seen on the Set Baseline dialog in Project Professional (Last Saved on...).

    One exanplme shows 27/5/18 in OData and 16/7/17 in Project Professional.

    The TaskBaselineModifiedDate in the Task_Baselines OData table, is consisitent with the ProjectBaselineModifiedDate.

    As aresult, we can't show in Power BI reports the real baseline date.

    Can somone suggest a solution?