MS Proj 2007 Finish Variance RRS feed

  • Question

  • I created an arbitrary activity with

    Dur PS PF
    20 edays 12/19/2011 8:00 1/8/2012 8:00

    After making baseline of it, below table shows update with 4 and 5 days delay in start in Variance Table. Is there anything we should know why the start and finish variance do not appear right please?

    PS PF Baseline start Baseline finish Start var Finish var
    12/19/2011 8:00 1/8/2012 8:00 12/19/2011 8:00 1/8/2012 8:00 0 days 0 days
               
    12/23/2011 8:00 1/12/2012 8:00 12/19/2011 8:00 1/8/2012 8:00 12 days 12 days
               
    12/24/2011 8:00 1/13/2012 8:00 12/19/2011 8:00 1/8/2012 8:00 15 days 15 days

     KC

    Monday, December 19, 2011 7:55 AM

Answers

  • In elapsed durations, Project ignores calendars when calculating the schedule. Pls test your scenario with day entry instead of eday entry.
    Monday, December 19, 2011 10:05 AM

All replies

  • Oh

    I guess 1 calendar = 3 x 8 hr days, so 4 calendar days = 12 days delay.

    Any other advice please?

    KC 

    Monday, December 19, 2011 8:05 AM
  • In elapsed durations, Project ignores calendars when calculating the schedule. Pls test your scenario with day entry instead of eday entry.
    Monday, December 19, 2011 10:05 AM
  • It looks like you are using the 24hours calendar in the project.  Check Project > Project Information to see what is set as the project calendar.  You are correct, you still have 1 day = 8 hours (Tools > Options) but you are allowing 24 working hours per day.

    I hope this helps.

    Julie

    Monday, December 19, 2011 1:53 PM
    Moderator