Project 2010 Standard - Inactivate Button missing in Task>Schedule area RRS feed

  • Question

  • I'm using MS Project 2010 Standard and the "Inacticate Button" is not available under the Tasks Ribbon, "Schedule" section. What's up? Surely I should not have to buy Professional to get this function? It is NOT discussed in any MS version comparisions.
    Thursday, February 9, 2012 5:27 PM

Answers

  • Lowell,

    Sorry to break the bad news...but the inactivate button is only available in the Professional version.


    Gregg D. Richie, PMP, MCTS; Author, Microsoft Project 2010, Microsoft Official Academic Course Series

    • Proposed as answer by Ismet Kocaman Thursday, February 9, 2012 7:44 PM
    • Marked as answer by Lowell F Thursday, February 9, 2012 8:08 PM
    Thursday, February 9, 2012 5:52 PM
  • It's here at: http://www.microsoft.com/project/en-us/project-pro-2010-editions.aspx
    • Marked as answer by Lowell F Thursday, February 9, 2012 8:07 PM
    Thursday, February 9, 2012 7:44 PM

All replies

  • Lowell,

    Sorry to break the bad news...but the inactivate button is only available in the Professional version.


    Gregg D. Richie, PMP, MCTS; Author, Microsoft Project 2010, Microsoft Official Academic Course Series

    • Proposed as answer by Ismet Kocaman Thursday, February 9, 2012 7:44 PM
    • Marked as answer by Lowell F Thursday, February 9, 2012 8:08 PM
    Thursday, February 9, 2012 5:52 PM
  • Thanks Gregg... Is there a feature/function comparison matrix listing this (and other) "gotcha's"?

    Lowell

    Thursday, February 9, 2012 5:59 PM
  • It's here at: http://www.microsoft.com/project/en-us/project-pro-2010-editions.aspx
    • Marked as answer by Lowell F Thursday, February 9, 2012 8:07 PM