Project 2013 Burndown Chart RRS feed

  • Question

  • I see the new Project 2013 offers a burndown chart in the standard reports.  How does task progress need to be entered for the burndown chart to correctly report on task progress over time?
    Sunday, July 22, 2012 10:56 PM

All replies

  • I believe Heather's article here at http://blogs.msdn.com/b/project/archive/2007/11/14/we-re-back.aspx may provide some information on what progress data is needed to create a burndown report/chart.
    • Proposed as answer by Ismet Kocaman Wednesday, August 8, 2012 5:02 PM
    Sunday, July 22, 2012 11:35 PM
  • I was able to just update some tasks as 100% complete and it updated OK.

    What are you seeing?


    Brian Kennemer - Project MVP
    DeltaBahn Senior Architect
    endlessly obsessing about Project Server…so that you don’t have to.
    Blog | Twitter | LinkedIn

    • Proposed as answer by Ismet Kocaman Wednesday, August 8, 2012 5:02 PM
    Monday, July 23, 2012 1:51 AM
    Moderator
  • 8 new fields for burndown reports:

        Baseline0-10 Cumulative Work field  
        Baseline0-10 Remaining Cumulative Work field
        Baseline0-10 Remaining Tasks field  
        Cumulative Actual Work field
        Remaining Actual Tasks field  
        Remaining Cumulative Actual Work field
        Remaining Cumulative Work field
        Remaining Tasks field

    Regards.