Changes in MSP 2010, or am I missing something? RRS feed

  • Question

  • Hi All,

    I have run into two things that puzzle me, I hope someone can help me out.

    1. When I have a Fixed Work task and increase the duration, work is spread out over the days as expected. But the assignment level on the resource is still 100%. Should it not decrease?

    2. I have a Fixed Units/Effort Driven task that I increase duration on, and this causes work to increase also. Should it not remain unchanged, being a Effort Driven task?

    Cheers

    Lars