EV (BCWP) - problem RRS feed

  • Question

  • I saved 3 Baseline and setDate state in my project. I have problem with EV (BCWP), becauseI set in MSP 2010 Option on the Advanced tab in the “Baseline for Earned Value calculation” - Baseline 3.

    In the Task Usage view, everything is OK and the value of the EV (BCWP) is correct, but the same field in the view Gantt Chart in table Earned Value Schedule Indicators shows the value is incorrect, the other fields e.g. BCWS, ACWP are countedcorrectly.

    Compared thevalues ​​and came to the Project takes (calculated) BCWP of the Baseline not Baseline 3. In other test projects, everything is OK. Of course, this project is published on the Project Server.

    How I could fixed it?

    Kind regards for any help