none
How to update the Link Between Projects Dialogue to have additional task fields RRS feed

  • Question

  • Hi,

    In Project 2016 Pro, when we click on the "Links between Projects" under Project menu, it displays the external predecessors and external successors with the following fields Information:

    ID,Task, Type, Date, %comp, Differences

    Can we add additional fields to this dialogue? I mean any task custom field.

    Please suggest.

    Tuesday, September 12, 2017 9:59 PM

All replies

  • Sudhir,

    Sorry no. That window has a fixed format.

    As far as suggestions, you could filter on the External Task field. That will show all externally linked tasks. Or you could create a filter that looks for a slash ("\") in either the Predecessor or Successor field. That will show both source and destination tasks involved in the inter-project links. As long as you include your custom fields in the view table, they will show up with either filter.

    Hope this helps.

    John

    Tuesday, September 12, 2017 10:43 PM