Linked tasks - auto completion RRS feed

Answers

  • Hi,

    By linked, do you mean predecessors?

    No there is such a feature. But if you use the "mark on track" button, all the work before the status date will be automatically marked as completed, which makes more sense than doing this based on the links.

    Otherwise, you might need some VBA code.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    • Marked as answer by Anujaa Tuesday, October 13, 2015 1:37 PM
    Monday, October 12, 2015 9:21 AM