Microsoft Project Recource Calendar RRS feed

  • Question

  • I have created a standard calendar with exception dates, I have one resource that is going to work on an exception date. how do I change their calendar to make the non-working day, working?
    Tuesday, May 12, 2015 2:03 PM

Answers

  • AmyR1982

    Add an exception on the Resource Calendar for the resource who will be working on the exception day.  Click on the Details tab for the exception and select the Working Times.  Setting the working times now makes the exception day a working day for this resource.

    Hope this Helps