Assignment baseline data not appearing in reporting database RRS feed

  • Question

  • Hi,

    We have created some assignments in Microsoft project and baseline hours are appearing in PWA(In Resource Assignments), but the same data is not appearing in Assignment baseline tables in database.

    Assignments are appearing in Assignment user view but baseline values are null.

    Baseline data is appearing in task user view.

    We are using Microsoft project 2013

    please tell me, the reason why data is not populating in assignment baseline table?

    Thanks,

    Sarath.

    Tuesday, May 12, 2015 11:01 AM

All replies

  • Hi Sarath,

      Well which SP version are you using in your environment?

    Make sure Project was published successfully check your Queue jobs, if all jobs are executed successfully for the particular project. 

    Try using one of the references in below to extract information from the table directly, possibly in view a different field is used. 

    https://msdn.microsoft.com/en-us/library/aa164674(v=office.10).aspx


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Tuesday, May 12, 2015 11:51 AM