    Is it possible to manage several different workflows in the same instance of Project Server 2013?

    If yes, how to manage the Stages in the Workflow Stages page of PWA?

    Thanks 


    • Edited by WLID1966 Sunday, September 13, 2015 8:31 AM
    Sunday, September 13, 2015 8:21 AM

Answers

  • Yes, it is possible to create and manage several workflows in the same instance of Project Server 2013.

    However you don't find this option in "Server Settings" or other parts of the administration user interface.

    Workflows are created in SharePoint Designer or programmed in Visual Studio.

    After creation your workflow of choice should be associated with your Enterprise Project Type, so that when you create a project of the specific type it follows the corresponding workflow.

    Normally you define business specific custom phases and stages and use them in the workflow.