RBS and Material resources (PWA 2007) RRS feed

  • Question

  • Hello,

    I have a small RBS on 3 levels : Program Managers\Project Managers\Resources in Project Server 2007.

    But I have some Material resources and some Cost resources which are not in the RBS. So the Project Managers cannot see them in the Built Team dialog.

    How to manage this case?

    Thanks

    Tuesday, February 28, 2012 12:58 PM

Answers

  • Hi,

    is the list of material and cost resources (more or less) static? If so, you could create a new category for these resource (MaterialAndCost). Add these resources in the resource section to Selected Ressources (Only the available resources indicated). Add necessary views (for PWA) in view section, like Team Builder, Resource Center views,....

    Add group of your project managers in section Users and Groups and define necessary actions Assign Resource, View Enterprise Resource Data,...)

    Does that help?
    Barbara

    • Marked as answer by WLID1966 Tuesday, February 28, 2012 1:50 PM
    Tuesday, February 28, 2012 1:18 PM
    Moderator

All replies

  • Hi,

    is the list of material and cost resources (more or less) static? If so, you could create a new category for these resource (MaterialAndCost). Add these resources in the resource section to Selected Ressources (Only the available resources indicated). Add necessary views (for PWA) in view section, like Team Builder, Resource Center views,....

    Add group of your project managers in section Users and Groups and define necessary actions Assign Resource, View Enterprise Resource Data,...)

    Does that help?
    Barbara

    • Marked as answer by WLID1966 Tuesday, February 28, 2012 1:50 PM
    Tuesday, February 28, 2012 1:18 PM
    Moderator
  • Great! That works!

    Thanks Barbara

    Tuesday, February 28, 2012 1:52 PM