Resource forecasts in Master Plan sub-projects not included in Portfolio Analysis Resource Analysis? RRS feed

  • Question

  • Enterprise Server 2010, SP1, June 2012 CU.  Created a published Master Plan with five sub-projects linked Read-only.  One of the sub-projects has only a Resource Plan with Calculate From set to Resource Plan and estimates through the analysis period, the other schedules have enterprise resources with task assignments having Work estimates through the analysis period.  None of the resource forecasts are showing up in the analysis run.
    Wednesday, March 6, 2013 6:15 PM

All replies

  • Alan,

    You might have already checked these, but just trying to confirm:

    1. You have checked the check box for time-phased Resource Analysis when setting up the Portfolio Analysis
    2. You selected a Resource Level field that can be used to compare demand vs supply
    3. Your resources are all tagged with that resource level custom field
    4. All project Plans are published



    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    • Proposed as answer by Renke Holert Wednesday, March 6, 2013 10:25 PM
    Wednesday, March 6, 2013 9:27 PM
    Moderator
  • Prasanna:  Thanks for the response.  Yes, all four items you noted are correctly selected or completed.

    Alan

    Monday, March 18, 2013 6:15 PM