MS-Project Server 2010: More than 11 Baselines? RRS feed

  • Question

  • Hello together,

    we using the MS-Project 2010 Server Solution and have a question to the baselines:

    It is possible to save/create more than the 11 Baselines that are predefined in MS-Project?

     

    Thanks for your help,

    Tobias

    Monday, August 22, 2011 12:23 PM

Answers

  • Hi Tobias,

    MS Project has 11 Baselines which save some 14 variables of Dates/Work/Cost etc. Then once 11 are exhausted you can use 10 Interim Plans which captures Start and Finish Dates in Start1/Finish1 fields. Other then this you can utilise 10 Dates fields to save your snapshots. So I guess these are enough for a Project Life Cycle.


    Sapna S
    • Marked as answer by der_toby Monday, August 22, 2011 3:34 PM
    Monday, August 22, 2011 12:35 PM
    Moderator

All replies

  • Hi Tobias,

    MS Project has 11 Baselines which save some 14 variables of Dates/Work/Cost etc. Then once 11 are exhausted you can use 10 Interim Plans which captures Start and Finish Dates in Start1/Finish1 fields. Other then this you can utilise 10 Dates fields to save your snapshots. So I guess these are enough for a Project Life Cycle.


    Sapna S
    • Marked as answer by der_toby Monday, August 22, 2011 3:34 PM
    Monday, August 22, 2011 12:35 PM
    Moderator
  • Ok, thx for your support!
    Monday, August 22, 2011 3:34 PM
  • You are most Welcome Tobias.
    Sapna S
    Tuesday, August 23, 2011 5:26 AM