How to show only two weeks of tasks in calendar view RRS feed

  • Question

  • Hi everyone,

    I'm stuck for several days with the calendar functionnality with Project Server.

    I would like that the calendar shows only two weeks instead of 4.

    Could you tell me if it is possible? if yes, how?

    Thank you in advance.

    Monday, September 5, 2016 7:58 AM

All replies

  • Hi Najar,

    You want to do this for just only one month or want to keep that calendar for quite long?

    I guess you can achieve it through editing you enterprise calendar, to do so you have to navigate to server settings>Enterprise Data>Enterprise calendars > Select the calendar which you want to edit (use ie 8 or more to do so)

    Once calendar gets open in MS Project

    • Click on project tab
    • Change working time
    • Select the set of weeks which you don't want to show and write leave or holiday or whatever under the exception
    • Click on details from right side and select it on the basis of monthly yearly or so.
    • Click Ok and ok.

    Let me know if the solution works for you or you are looking for some other things

    Please mark the answer if it helps.

    Regards

    Abbas Khan

    Monday, October 24, 2016 12:04 PM