Importing Resource Actual Hour and Dates with XLS to 2010 Pro and Publishing to Server Not Working RRS feed

  • Question

  • I am trying to create ~100 "as-built"schedules to MSP Server 2010 (on SP 2010).  I would like to create them in Pro, then import an XLS with actual (Generic) Resource Name, Work (hours), Actual Start/Finish, etc.  The problem is after I create a shell in Pro and upload it to the server, subsequent changes based on my Excel Template don't stick.  I can see the imports in Pro, then Save/Publish/Check-In to the server, but I don't see the updates in PWA.  What's strange though is then I download the project from the server and the imported data is still there.  I have checked Server Settings that would seem relevant; such as, Timesheet Setting and Defaults and everything seems to be fine.  I feel like there is some button I need to push to propagate the (non-timesheet) data out there.  I am the admin and have rights to everything.  What am I missing?