Upgrade from Lync 2013 to skype for business 2015 RRS feed

  • Question

  • Good day

    I am currently running Lync 2013 enterprise with 3 servers in each of the two load balanced team of servers.
    SQL is mirrored, I want to plan an upgrade . I am thinking of side by side upgrade.

    what is the best way to upgrade to Skype for business 2015

    Please help.


    • Edited by Sthamza Thursday, June 23, 2016 8:25 AM
    Thursday, June 23, 2016 8:14 AM

Answers

  • If you use W2012R2 as OS, you can do a inplace-upgrade. With an side by side Migration you can do also a perfect migration.

    Create a entreprise pool with 3 Server and SQL mirroring and move some user for testing to the new pool.

    If you have moved all users, do a inplace upgrade of the edge Server.


    regards Holger Technical Specialist UC

    • Proposed as answer by Liinus Tuesday, June 28, 2016 4:32 AM
    • Marked as answer by Niko.Cheng Saturday, July 9, 2016 3:17 AM
    Thursday, June 23, 2016 10:51 PM
  • Hi Thami Dlamini,

    Based on my understanding, you could upgrade directly with your environment.

    Since you have a back-end database that is mirrored then you will see both the Principal and the Mirrored databases show up when you publish the topology using Topology Builder. Make sure all of the databases are running on the Principal and only select the Principal.

    For details, please refer to

    https://technet.microsoft.com/en-us/library/dn951371.aspx?f=255&MSPPError=-2147217396

    Best regards,

    Alice Wang

    • Proposed as answer by Liinus Tuesday, June 28, 2016 4:32 AM
    • Marked as answer by Niko.Cheng Saturday, July 9, 2016 3:17 AM
    Tuesday, June 28, 2016 2:39 AM

All replies

  • If you use W2012R2 as OS, you can do a inplace-upgrade. With an side by side Migration you can do also a perfect migration.

    Create a entreprise pool with 3 Server and SQL mirroring and move some user for testing to the new pool.

    If you have moved all users, do a inplace upgrade of the edge Server.


    regards Holger Technical Specialist UC

    • Proposed as answer by Liinus Tuesday, June 28, 2016 4:32 AM
    • Marked as answer by Niko.Cheng Saturday, July 9, 2016 3:17 AM
    Thursday, June 23, 2016 10:51 PM
  • https://jaapwesselius.com/2015/05/12/upgrade-lync-2013-to-skype-for-business-2015-step-by-step/
    Friday, June 24, 2016 6:01 AM
  • Hi Thami Dlamini,

    Based on my understanding, you could upgrade directly with your environment.

    Since you have a back-end database that is mirrored then you will see both the Principal and the Mirrored databases show up when you publish the topology using Topology Builder. Make sure all of the databases are running on the Principal and only select the Principal.

    For details, please refer to

    https://technet.microsoft.com/en-us/library/dn951371.aspx?f=255&MSPPError=-2147217396

    Best regards,

    Alice Wang

    • Proposed as answer by Liinus Tuesday, June 28, 2016 4:32 AM
    • Marked as answer by Niko.Cheng Saturday, July 9, 2016 3:17 AM
    Tuesday, June 28, 2016 2:39 AM