Assign resources to tasks unequally RRS feed

  • Question

  • Hi guys,

    So my problem is as following:

    I have a task and let's say that it takes 10 hours of work to complete this task. And there are two resources put on this task. Resource 1 worked 3 hours on this task and Resource 2 worked 7 hours on this work. How can you do this?

    Werner

    Friday, October 20, 2017 2:49 PM

Answers

  • I think I solved the problem. In the Resource Usage I add manually the hours worked on a task for each resource.
    • Marked as answer by Werner97 Friday, October 20, 2017 3:07 PM