Change default working times and costs RRS feed

  • Question

  • In project 2016, the default working time is set to hours. I need to set it to days to comply with the types of projects we do. Also the default resource costs are likewise in hours, and I need costing to be in days.

    Any help would be appreciated.

    Thank you

    Friday, October 21, 2016 4:47 AM

All replies

  • Hi,

    you can change the units in File - Options - Schedule.

    And you can also enter resource rates by day, just adding days as unit.

    Does that help?
    Regards
    Barbara


    To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find an appropriate solution faster. Thanks for your support!