Unwanted Actual work RRS feed

  • Question

  • Hello

    we have project server 2010 sp2, in some project some resource have actual work that they dont enter them in timesheet or my work !

    has anyone this problem?

    i cant understand why & from where, this actual work is automatic insert in task

    Single Entry Mode is on

    Only allow task updates via Tasks and Timesheets is on

    Allow future time reporting is off (but in some days, some project had unwanted actual work in future)

    and There is no history for this assignment in task detail

    I am disappointed

    please help
    Thursday, November 10, 2016 3:40 PM