Start date & timescale options RRS feed

  • Question

  • Hi,

    I have set a start date for the project, and then use the : "M1, M2, M3 ... (from start)" option for the timescale, but my start date for the project appears on M3, and not M1! Has anyone an explanation for this, and how to fix it?I am using an MS project 2013 trial version.

    Felipe

    Saturday, August 10, 2013 1:33 PM

All replies

  • FST89 --

    How exactly did you set the Start date of the project?  Did you click the Project tab, click the Project Information button, and then set the Start Date value in the Project Information dialog?  Let us know and we will try to help.


    Dale A. Howard [MVP]

    Saturday, August 10, 2013 7:30 PM
    Moderator