  • Running Project Server 2010 / SharePoint 2010.  When I create a project, I'm not able to insert or delete tasks under the default views.  Originally this was possible.  One new view has been created with similar view configurations and the insert and delete options are available for this view but no others.  Have looked through the Project Permissions as well as the Server Setting -> Manage Users/Groups with no luck.

    Fuel

    Thursday, June 7, 2012 1:34 PM

Answers

  • This is by design as only task views are editable.

    Resource views and Assignment view are derived info related to the relationship betweeen the Task and the assigned Resource(s).

    --Treb

    • Marked as answer by Fuel451 Wednesday, June 20, 2012 2:22 PM
    Tuesday, June 12, 2012 7:01 PM
    Moderator

All replies

  • Fuel,

    Where are you trying to add/delete tasks? Project Pro or PWA?

    Assuming it is PWA, which view are you trying to do thsi in? Not all views are editable in PWA.


    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    Friday, June 8, 2012 5:20 PM
    Moderator
  • Trying to add/delete tasks from the PWA web site.  Looks like the default Assignments views and Resources views are not editable.  The Tasks views are editable as are custom views.  If this is by MS's design no worries.  I just don't see anywhere to lock a view down to view-only.

    Fuel


    Fuel

    Tuesday, June 12, 2012 3:07 PM
  • This is by design as only task views are editable.

    Resource views and Assignment view are derived info related to the relationship betweeen the Task and the assigned Resource(s).

    --Treb

    • Marked as answer by Fuel451 Wednesday, June 20, 2012 2:22 PM
    Tuesday, June 12, 2012 7:01 PM
    Moderator
  • Agreed with Treb & Prasanna, more explanation by Brian.
    http://social.technet.microsoft.com/Forums/pl-PL/projectserver2010general/thread/79f85727-24e1-4626-ad8d-55f4b87ce1f7


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    Wednesday, June 13, 2012 8:55 AM