Is MSP capable of calculating the Planned percentages of activities? RRS feed

  • Question

  • Rather thas manually enter the percentage progress for the baseline activities (i.e. planned percentages), is MSP capable of calculating these automatically?           
    Wednesday, October 17, 2012 7:06 AM

Answers

  • Hi William,

    You can use the Project Update option to calculate and update your planned % completed. Go to Project -> Update Project -> Update Work as Completed through (Status Date or Current Date).

    This will update all tasks % complete as planned value.


    Sapna Shukla

    Wednesday, October 17, 2012 9:51 AM
    Moderator

All replies

  • I can see this turning into a long conversation, but here goes anyway.

    A bit more explanation is going to be essential.

    What exactly is it that you are hoping is calculated automatically?

    What is a "baseline activity"? Is it a task which has been baselined?

    You will probably need to explain how you go about updating progress and re-scheduling, but I can probably guess.

    When you say "manually enter the percentage progress", does this mean that you type in a number into the % Complete field?

    If so, where do you find this field? In the task information, or as a column in the tracking table, or as an inserted column in the entry table?

    Wednesday, October 17, 2012 8:05 AM
  • Hi William,

    You can use the Project Update option to calculate and update your planned % completed. Go to Project -> Update Project -> Update Work as Completed through (Status Date or Current Date).

    This will update all tasks % complete as planned value.


    Sapna Shukla

    Wednesday, October 17, 2012 9:51 AM