Current Max Units - Custom Availability Detected - Edit in Project Pro RRS feed

  • Question

  • When in the resource center and editing a resource the following is displayed in the Resource Max Units field

    Custom Availability Detected - Edit in Project Pro

    What setting controls this and will allow the Max Units % to be entered into this field?

    Thank you -


    lbr

    Wednesday, November 28, 2012 8:00 PM

All replies

  • Sounds like someone entered a custom availablity contour in Project Pro for the resource. If you open the Resource from Resource Center using the Open button, they'll open in Project Pro. Double click on the resource.

    In the lower left hand corner of the dialog, you will see an area to enter Available From/To grid. Chances are someone has entered different Max Units by month, quarter, etc.

    Treb Gatte | @tgatte | http://AboutMSProject.com

    Wednesday, November 28, 2012 8:10 PM