Does MSP 2010 do resource sheduling automatically ? RRS feed

All replies

  • If you mean does it make resource assignments: No.  That job of user (Project Manager and Team)

    If you mean will it compute a schedule based on your model of durations, logic, assigned resources, and then show you the schedule of when the resources required: Yes, it does that and that's the purpose of the tool.

    You can disable it one of two ways: use Project's Manual Scheduling method (which puts all onus on you to do the complex calculations), or use another tool.  


    --rms www.rmschneider.com

    Thursday, November 1, 2012 8:35 AM
  • Hi,

    I thonk you talk (amongst other possibilities) of Resource Leveling i.e. Project delaying tasks when a resurce is overallocated. This CAN be automatic or manual depending on a setting in Leveling Options (Resource ribbon). Default is manual.

    Greetings,

    Thursday, November 1, 2012 7:45 PM