    In a brand new Project Online environment, I have an “issue” with resource constraints in portfolio analysis where resource assignments are not appearing in the Project Requirements


    In the screen below, all resource in the project called SWIFT are assigned from May to Oct

    The view is also good on the Resource assignment on the server with proves that the information is published


    I have tried to reload the resources from the constraint Options menu, publish the project but nothing makes the numbers appears in the resource constraints

    I did some more testing with another project with tasks ending before October and tasks in October 2016. it appears that as soon as the finish date is after October, everything before is pushed to 0



    Thanks a lot


    Jérome Charlon - Senior Project Server Architect - MCP-MCTS

    Friday, May 27, 2016 4:05 AM

All replies

  • I can add to that that while I am using doing the analysis in a quarterly basis, the calculation looks good.

    thanks


    Jérome Charlon - Senior Project Server Architect - MCP-MCTS

    Monday, May 30, 2016 12:42 AM