none
Replacing Resources RRS feed

  • Question

  • In our company ,recently all users have been migrated to Windows 10 and have new user IDs.

    For this I in my project I want to substitute the old Resource name with the new Resource name.

    I opened the Build Team from Enterprise Dialoge Box and replaced a resource.

    The following thing occured:

    All work that was already completed stayed with the old resource. All remaining work was assigned to the new Resource.

    For Tasks for which the old Resource was assigned to at 30%  the new Resource is now allocated at 100% for the remaining work.

    Questions:

    1. How can I substitute a Resource 1:1 (new user ID for old user ID) and also maintain the actual work?

    2. How can be assured that the new Resource maintains the same assignment units for the remaining work?

    Thank you for your answer!

    Regards,

    Heiner

     

    Friday, September 2, 2016 9:11 AM