none
MSPS- Timesheet Pre Populated Planned hours. RRS feed

  • Question

  • Hi All,

    This is my first post in this forum, I have pre populated hours in planned hours row, can any one suggest how to get this rid off.

    See attached screenshot for more cliarty

    Thanks

    AK


    Friday, November 15, 2013 9:27 AM

All replies

  • Sorry - Site admin did not allow me to post screenshot.
    Friday, November 15, 2013 9:28 AM
  • Hi Anand,

    Could you please clarify:

    In which view did you enter data? Task Usage? Resource Usage?

    If it is in a usage view, is it on a line of a task? a Resource? An assignment( names in Italic)?

    What is the name of the row? Work? Actual Work (there is no row called planned hours)?

    Greetings,

    Friday, November 15, 2013 9:41 AM
    Moderator
  • Hi AK,

    If your are talking about planned hours in a timesheet view, then you can hide planned hours in clicking on "planned" in the "show/hide" group of the ribon.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    Friday, November 15, 2013 1:50 PM
    Moderator