DPM 2012 Short term protection full every 2 weeks RRS feed

  • Question

  • I'm looking answer for the following question.

    Is it possible to set short term protection to tape according to schedule: full backup - every 2 weeks, incremental every working days?

    thanks in advance


    br kyrik

    Monday, May 13, 2013 6:51 AM

All replies

  • Hi,

    For daily D2T backups, you have two choices:

    Only full backup, and you can choose the day(s) of the week.
    Full and Incremental backup, you choose Day for the FULL, and what remaining days you want incremental backups done.

    There is no provision of not taking a FULL backup once a week. 


    Please remember to click “Mark as Answer” on the post that helps you, and to click “Unmark as Answer” if a marked post does not actually answer your question. This can be beneficial to other community members reading the thread. Regards, Mike J. [MSFT] This posting is provided "AS IS" with no warranties, and confers no rights.

    Friday, May 17, 2013 7:47 PM