MS Project - Timeline Customization RRS feed

  • Question

  • In the timeline view in Project 2000 my timescale is displayed in quarters (1st, 2nd...), I would like to change that to months/ years.

    • Moved by Max Meng Monday, July 15, 2013 1:59 AM
    Friday, July 12, 2013 7:21 PM

All replies

  • Hi,

    I don't have 2000 around any longer to verify, I but I believe the steps below will get you there.

    1. In the menu select Format > Timescale
    2. Set the Major scale to years and the minor scale to months.
    Monday, July 15, 2013 3:24 PM